FREE DOWNLOAD · 4-PAGE CHECKLIST

KASITA CRAFTERS — FREE GUIDE

The ADU Permit

Checklist

Everything to confirm before you apply for an ADU permit in California — zoning, setbacks, utility hookups, and the mistakes that cause delays.

01

Does your lot qualify? Zoning & eligibility

02

Setbacks, utilities & what to submit

03

The common mistakes that stall approvals

04

Your realistic permit timeline

Kasita Crafters — homes for everyone

kasitacrafters.com

PART 1 — ZONING & ELIGIBILITY

Does your lot qualify?

Since 2020 (AB 68, AB 881, SB 13), ADUs are allowed by right on most California residential lots. Confirm the basics before you design anything.

Your lot has a single-family or multi-family residence

⚠ PRO

City's max ADU size checked (state allows up to ~1,200 sqft)

ADU count confirmed — most lots allow 1 ADU + 1 Junior ADU

Owner-occupancy not required (removed statewide for ADUs)

Height limit reviewed — detached ADUs generally up to 16 ft

HOA CC&Rs reviewed for any restrictions

⚠ PRO

Historic district or overlay zone flagged

⚠ PRO

REMEMBER

Rules vary by city and change often. Verify with your local building department — we confirm yours during your free evaluation.

Kasita Crafters — ADU Permit Checklist

Page 01 of 03

PART 2 — SETBACKS, UTILITIES & SUBMISSION

What to confirm and submit.

4 ft side and rear setbacks for new detached ADUs

⚠ PRO

Front setback matches your primary residence

Utility plan decided — water, sewer, and electrical

Water meter / sewer capacity confirmed with provider

⚠ PRO

Parking — none required within ½ mile of transit

Site plan, floor plan & elevations ready (prefab includes these)

Title 24 energy compliance docs included

Structural calcs for units over 500 sqft or on a foundation

TYPICAL PERMIT TIMELINES

Pre-approved city plans

21–30 days

Standard single-family lot

30–60 days

Junior ADU (converted space)

2–3 weeks

Complex lots / older infrastructure

60–120 days

Kasita Crafters — ADU Permit Checklist

Page 02 of 03

PART 3 — BEFORE YOU SUBMIT

Five things that stall approvals.

Avoid these five and your application moves through cleanly. Every one of them is in your control.

01

Skipping the pre-application meeting with your building dept

02

Underestimating utility upgrades — undersized meter or sewer

03

Missing the 4-ft setback on a tight lot

04

No drainage plan for the pad

05

Forgetting Title 24 or structural docs on units over 500 sqft

Kasita handles the permit package for you.

Pre-drawn plans, Title 24, structural sign-offs, and HCD certification come done. You provide the site and utility info — we handle the rest.

BOOK YOUR FREE EVALUATION →

Kasita Crafters — ADU Permit Checklist

Page 03 of 03